Twenty years of environmental and social work on hydropower, pumped storage and associated infrastructure.

Projects before 2023 were delivered by Simon Howard as Principal Environmental and Social Consultant at Mott MacDonald (2016–2023) and as Sustainability Specialist at the International Hydropower Association (2011–2016).

ESDD & lender advisory  ·  ESIA  ·  Screening  ·  Developer support  ·  HSS  ·  Programmes

Two rivers meeting

Lender advisory

ESDD, lender advisory and monitoring

Baynes HPP, Angola/Namibia

Transboundary, Kunene River · SMEC · 2024–present

ESDD to the IFC Performance Standards: review of ESIAs, Resettlement Action Plans and stakeholder engagement.

Ngoulmendjim HPP, Gabon

83 MW and 80 km transmission line · AfDB · 2022–23

ESDD and lender’s technical advisor.

Sahofika HPP, Madagascar

192 MW and 130 km transmission line · AfDB · 2019–23

ESDD and lender’s technical advisor against the IFC Performance Standards and AfDB safeguards.

Kinguele HPP, Gabon

35 MW · Asonha Energie (AfDB, DBSA, IFC) · 2019–23

Lender’s technical advisor: full E&S review against lender requirements and actions to achieve conformance.

Alpaslan 2 HPP, Türkiye

280 MW · MUFG for a lender consortium · 2019–23

Lender’s technical advisor through financial close, construction, commissioning and operation.

Seli HPP, Sierra Leone

143 MW, Bumbuna expansion and Yiben · Joule Africa · 2018–23

Lender’s technical advisor: ESDD against the IFC Performance Standards.

Gulpur HPP, Pakistan

100 MW run-of-river · lenders incl. ADB and IFC · 2015–23

Led E&S construction monitoring, then operational monitoring.

Tarbela 5th Extension, Pakistan

WAPDA, World Bank financed · 2019–23

Owner’s engineer E&S: contractor prequalification, tender evaluation and quarterly construction monitoring.

Siti 1 & 2 and Lubilia, Uganda

5–15 MW · Elgon Hydro · 2016–23

Quarterly construction monitoring and risk advice.

Khobi HPP, Georgia

55 MW · Meridiam · 2017

ESDD and a roadmap of deliverables to meet lender requirements before financial close.

Nenskra HPP, Georgia

280 MW · EBRD · 2016

ESDD and preparation of the lender’s action plan.

Impact assessment

Environmental and social impact assessment

Tarbela 5th Extension, Pakistan

Incl. 325 MW floating solar · World Bank financed · 2019–23

ESIA with cumulative impact assessment for the transmission line, ESIA for floating PV, and management of survey teams and consultation.

Mpatamanga HPP, Malawi

With regulating dam · IFC · 2020–23

Led hydrology, hydrogeomorphology and water quality impacts; authored project description and alternatives chapters.

Pavua HPP, Mozambique

120 MW greenfield dam · EleQtra · 2018–19

ESIA project manager to Mozambican law and the IFC PS; water, alternatives and cumulative impact chapters.

Neretvica HPPs, Bosnia and Herzegovina

Cascade of 15 small HPPs · EBRD · 2018

Managed the ESIA and critical habitat assessment; drafted key sections.

Jilamito HPP, Honduras

14.5 MW · INGELSA–IESA, for OPIC and IDB · 2019

Desk-based ESIA addendum aligned to the IFC PS, disclosed by OPIC.

River at sunset

Where we have worked

Projects across sub-Saharan Africa, South and Southeast Asia, the Caucasus, Europe, Latin America and New Zealand.

Early stage

Red flag reviews, screening and gap analysis

Pumped storage acquisition, Wales

100 MW · confidential utility client · 2019

E&S red flag review as part of acquisition due diligence.

Afghanistan hydropower portfolio

IFC · 2018

E&S screening of candidate projects; two sites prioritised for development.

Tsanga HPP, Zimbabwe

2.5 MW · Lion’s Head Global Partners · 2019–20

Gap analysis of the ESIA and action plan against good international industry practice.

Mwambwa HPP, Zambia

EleQtra · 2016

Red flag review ahead of a full ESIA; the project was paused, saving significant investment.

For sponsors

Developer E&S support

Mphanda Nkuwa HPP, Mozambique

EDF · 2024

E&S strategy, terms of reference and E&S team design aligned with the IFC Performance Standards.

Ngonye HPP, Zambia

180 MW run-of-river · EleQtra · 2018

Owner’s engineer: downstream flow regime optimised for environmental, social and economic objectives.

Shuakhevi HPP, Georgia

187 MW · AGL · 2016

On-site secondment during construction: new ESMS, local capacity building and close-out of lender commitments.

Certification

Hydropower Sustainability Standard and Protocol assessments

Cahora Bassa HPP, Mozambique

Operation · HCB · 2025

HSS assessor; also a 2018 Protocol review for the World Bank.

Corrie Glas pumped storage, Scotland

Preparation · SSE · 2025

HSS lead assessor.

Clyde and Roxburgh, New Zealand

752 MW, operation · Contact Energy · 2023

HSS lead assessor, supporting Climate Bonds certification.

Baleh HEP, Malaysia

1,285 MW, implementation · Sarawak Energy · 2023

HSS lead assessor; also a 2021 Protocol review.

Jatiluhur HPP, Indonesia

185 MW, operation · PJT II · 2023

HSS acting lead assessor, team of six.

Chuwa HPP, Nepal

250 MW, preparation · Bizbell Energy · 2023

HSS acting lead assessor.

Earlier assessments

Sinop, Brazil (IHA ESG tool, 2018), and Protocol assessments from 2011 to 2015 including Blanda and Hvammur (Iceland), Keeyask (Canada), Gavet (France), Santo Antônio (Brazil), Sogamoso and Cañafisto (Colombia), Sava River (Croatia), Kabeli A (Nepal), Nam Lik (Laos) and early-stage projects for Ghana’s Ministry of Power.

Earlier work

Capacity-building programmes and earlier career

World Bank, Zambezi basin

2015–16

Training, internal assessments and management system support for the basin’s four main hydropower operators.

Norad, Nepal and Myanmar

2013–16

Capacity building for a developer in Nepal and government in Myanmar, including EIA process review.

European Commission

2010–15

A four-year programme promoting the Hydropower Sustainability Assessment Protocol across the EU.

AusAID, Vanuatu

2010–11

Project manager for the National Rural Electrification Plan, including E&S assessment.

Laos Institute of Renewable Energy

2009–10

Rural electrification and water supply for communities around a mine, including ESIA.

Max Fordham

2005–08

Trained as a mechanical and electrical engineer, specialising in renewable energy.

Next step

Need a CV for a bid?

We’re happy to provide full CVs and project references for proposals, and to join consortia as a specialist associate.

Get in touch